Indiana Department of Transportation sent this bulletin at 05/30/2017 06:28 PM EDT
JOHNSON COUNTY, Ind. – Indiana Department of Transportation’s $84 million added travel lanes project on Interstate 65 in Johnson County will require restrictions on State Road 44 at the Franklin exit beginning next Monday (JUNE 5).
MONDAY June 5 – Mill and patch S.R. 44 northwest and southwest ramps with closures during daytime hours; each ramp will reopen once milled.
Pave and set Raised Pavement Markings (RPMs) on I-65 northbound and southbound between mile markers 95.0 and 88.5 during overnight hours; double right lane are closed—one reopens for daytime traffic.
TUESDAY June 6 – Mill and patch S.R. 44 northeast and southeast ramps with closures duringdaytime hours; each ramp will reopen once milled.
Pave and set RPMs along I-65 northbound and southbound outside shoulders between mile markers 95.0 and 88.5 during overnight hours; double right lanes are closed—one reopens for daytime traffic.
WEDNESDAY June 7 – Patch S.R. 44 ramps during overnight hours; each ramp closes during patching operations.
Place aggregate along I-65 northbound and southbound outside shoulders between mile markers 95.0 and 88.5 during daytime hours; single right lanes remain closed.
During overnight hours, pave I-65 northbound and southbound outside shoulders/slopewalls between mile markers 95.0 and 88.5; double right lanes are closed—one reopens for daytime traffic.
THURSDAY June 8 – Pave S.R. 44 northwest and southwest lanes/ramps during overnight hours; individual ramps close for paving, then reopen.
Place aggregate along I-65 northbound and southbound outside shoulders between mile markers 95.0 and 88.5 during daytime hours; single right lane remains closed.
FRIDAY June 9 – Pave S.R. 44 northeast and southeast lanes/ramps during overnight hours; individual ramps close for paving, then reopen.
Place aggregate along I-65 northbound and southbound outside shoulders between mile markers 95.0 and 88.5 during daytime hours; single right lane remains closed.
SATURDAY June 10 – Pave all S.R. 44 ramp shoulders during overnight hours; individual ramps close for paving, then reopen.
Place aggregate along I-65 northbound and southbound outside shoulders between mile markers 95.0 and 88.5 during daytime hours; single right lane remains closed.
All scheduled work is weather dependent.
Milestone is the state’s contractor for this 11-mile-long full-depth reconstruction of I-65 between Greenwood and Franklin which included bridge rehabilitation at Main Street/Greenwood, Whiteland Road, Hurricane Creek and S.R. 44